Roadworks overnight 5 Sept at Poles Lane
Extract from HCC letter to residents
Hampshire County Council Highways Department has written to nearby residents to tell them about overnight roadworks on the Poles Lane Roundabout.
The work is planned to run from 19:00 on Thursday 5 September 19:00 to 07:00 the following morning.
Mike Court of HCC advises us that they will try to do the noisier work towards the beginning of that period so as to minimise the risk of disturbing people’s sleep.
The letter says
Unfortunately as this is a traffic sensitive road these works will be carried out over night under three way traffic lights.
There may be some environmental impact i.e. noise, although we will endeavour to minimise this.
We have scheduled these works to take place on – 5th September 2013, between 1900hrs and 0700hrs.
If you have any questions or problems, please contact Hampshire Highways on the number above (01489 891038).