M3J9 Winnall Roundabout Resurfacing

M3J9 Winnall Roundabout Resurfacing Overnight 21-24 July 2020

The Parish Council has just received this letter with advance notice of overnight closures of  the Winnall Roundabout and all approach roads 

Main points

  • Starting Tuesday 21 July 2020 for four nights
  • Winnall Roundabout and all approach roads closed between 9pm and 6am
  • Diversions will be signposted

M3J9 Winnall Roundabout Resurfacing

Roadwork Information Enclosed

M3 Junction 9 Compound
Easton Lane
Winchester
Hampshire
SO23 7GR
10 July 2020
Ref: M3_605337

Dear Stakeholder,

M3 Junction 9 Winnall Roundabout (Winchester, Hampshire) Resurfacing

We will be resurfacing sections of the Winnall Roundabout, to ensure the carriageway surface remains in a safe condition for our customers.

For the safety of our workforce and customers we will be closing the roundabout and all approach roads over four nights (between 9pm and 6am) starting on Tuesday 21 July 2020.

Roads within the closure will include:

  • M3 junction 9 northbound exit slip road
  • M3 junction 9 southbound exit slip road
  • A272 Spitfire Link from the A31 roundabout
  • Easton Lane link between the Tesco roundabout and junction 9
  • A33 southbound link from Kings Worthy to junction 9

Various diversion routes will be in place during the closure using Winchester town centre (for closures of A34, Spitfire Link, southbound exit slip road, Easton Lane and the Kings Worthy link); and via the M3 and A303 for the closure of the northbound exit slip road.

Signage will be displayed on the M3 prior to junction 11 to allow road users the option to exit at the junction for Winchester.

Access will be maintained for emergency service vehicles on blue light calls only (under escort by a traffic management vehicle).

Please be aware that due to the current Covid-19 Pandemic, all our works are subject to change due to available resource by our Supply Chain, as well as possible adverse weather conditions – please check the yellow signs placed in advance at the junction for confirmation of the closures dates/timings.

We would like to apologise in advance for any inconvenience or disruption during our work. If you have any questions, or if you’d like you know more about our work please email us at or call us on 0300 123 5000.

Alternatively, to view our weekly report of full closures please visit https://highwaysengland.co.uk/roads, scroll down and under Roadworks click on ‘Check for Roadworks’, then scroll down and under Planned full closures click on ‘Check for Roadworks’ (this will open a Microsoft Excel file that will allow you to filter by day and road).

Yours faithfully
Kathryn Blofield
Communications Coordinator