M3 overnight closures – March 2015

M3 J11 to J9 overnight closures

 

Update from the Highways Agency – 16 March 2015

Latest news on the M3 quiet surface project.

It’s nearly done!

  • Carriageway resurfacing is about two thirds complete at present.
  • The work is programmed to be completed by the end of March.
Roadworks warning sign
Roadworks warning sign

Overnight closure details (subject to change)

  • The M3 will be closed between Junctions 11 and 8 for 5 nights, starting on 21 March.
  • This allows multiple sections to be worked on within the same closure. It would take longer as individual schemes because extra traffic management would be needed.
  • Advanced works notification signs have been put up on the network to tell motorists about the closures.
  • Other publicity about the closures includes letter drops to local residents and press releases to the media.
M3 traffic at night
M3 traffic at night

And finally..

  • Residual works such as road markings, anti-skid surfacing on the approach to junctions and traffic signal/sign loop installation are planned to be completed by May.

More information about work in progress

The details above should appear on the links listed below:

Slightly different info from the Highways Agency Newsfeed
M3 eastbound between J11 and J10 | Eastbound | Roadworks
17-03-2015 04:51 AM GMT
The M3 eastbound will be closed between junctions J11 and J9, due to roadworks, between 10 pm and 6 am, from 16 March 2015 to 2 April 2015.